Owner:
-
Contract Value:
4,316,000 EGP
-
Project Date:
2017-12-04
-
Projects Period:
3 Months
Data Center for Petrogas Co.
In cooperation with RITTAL Germany
Design and built Data Center for Petrogas Co.
NCTC Supply, install, Connect and test the following items:-
1- Uninterruptible Power Supply Modular System (UPS).
2- 2 CRAC unites for Data Center cooling.
3- Main and Sub- Main DISTRIBUTION BOARDS, LIGHTING & SOCKET PANEL AND HVAC PANEL.
4- Low Voltage Cables.
5- Lighting system “Lighting Fixtures and outlets”.
6- Wiring Devices and outlets.
7- Fire Alarm system Notifier brand and Fire Fighting.
8- Access Control and CCTV systems.
Rittal systems “Racks, CRACs, Containments, CMCIII and RIzone”.